Week 1 02/04/2024
Accomplishments:
● Back-end side discussed about code and new back-end member Mert learned the basics of the code. ● Code now works on machine-readable but still needs improvements. ● Front-end side looked at the design goal and planned the structure. ● System is integrated into computers.
Problems:
● There is an ETX character problem from the machine, back-end facing. ● Front-end system is going to be built from scratch.
TO-DO:
● Find a solution for the ETX character problem. ● Update inventory report to machine-readable version. ● Basic steps for the skeleton will be implemented. ● The login page will be designed as the beginning step.
Week 2 02/12/2024
Accomplishments:
● A new database will be designed and created until this week's meeting. ● The second part of the front end was created. ● The skeleton for the front end was created to have a well-organized structure.
Problems:
● Make the database match business requirements.
TO-DO:
● Update the database in the future and also update the code according to the new database. ● Starting to connect the front end with the database from the back end
Week 3 02/18/2024
Accomplishments:
● Get functions created. ● New attributes from the machine added to the database. ● The Front-end version on the git side has been updated. ● Get function connection has been planned.
Problems:
● None for the back-end.
TO-DO:
● Get more attributes from the machine. ● Starting to connect the front end with the database from the back end.
Week 4 02/25/2024
Accomplishments:
● Post function developed (added new commands). ● Front-end and Back-end have been connected with service. ● The third page has been improved to have a better UI for the user end.
Problems:
● Some of the commands are hard to store in the database re-design the database.
TO-DO:
● Get more attributes from the machine. ● Starting to connect the front end with the database from the back end. ● Going to continue with the next pages promising new features to the user-end.
Week 5 3/11/2024 - Spring Break
Accomplishments:
● Now the function retrieves according to the latest date. ● Get all history created. ● Updated post function further now sends more commands into the database. ● The errors which are for the leaks and etc. are demonstrated at the front end. ● A number of decimal controls have been added.
Problems:
● None
TO-DO:
● Going to continue with the next pages promising new features to the user-end. ● Going to add remaining commands.
Week 6 3/18/2024
Accomplishments:
● Connected and tested the new site. ● Added new section at UI showing symbols of alerts.
Problems:
● New site does not give information yet, working on it (probably going to be solved until this weeks meeting).
TO-DO:
● Going to add remaining commands. ● Going to include new sites into our UI.
Week 7 3/25/2024
Accomplishments:
● The system is updated for allowing the multiple sites(UI). ● The new cite is integrated to the system so now we can see the both sites not as hardcode. ● New Site table and commands created.
Problems:
● Still site numbers are limited.
TO-DO:
● Going to add remaining commands.
Week 8 4/1/2024
Accomplishments:
● Started working on the delete function. ● Design improvement for add site.
Problems:
● No problem for the front end for now.
TO-DO:
● Going to focus on other sections like authentication, settings etc.
Week 9 4/8/2024
Accomplishments:
● Now back end code is working by timer. ● New commands added. ● Front-end reconstructed so the refresh function can work ● Delete function is working properly in the front end
Problems:
● No problem for the back end and front end for now.
TO-DO:
● Going to focus on other commands.