Week 1

Title: Briefing

Date: 09/27/2021


Attendance: Merwyn Jones, Metehan Kundak, Berk Cohadar


Accomplishments

- Team members have sent necessary files to Professor Jones.

- Team members had meeting with Professor Jones.


Problems

- No problems for first week

To do

- Editting first wiki page

- To have informaiton about AllPawsInn's source code


Week 2

Title: Setup

Date: 10/3/2021

Attendance: Metehan Kundak, Berk Cohadar


Accomplishments

- Team members have examined AllPawsInn files that Professor Jones sent.

- Team members downloaded the source code to their local drivers.

- Team members reviewed user guide documentation and disscused about future actions



Problems

- Team members need to get used to the coding language components.

- Team members need to get familiar with PyQt designer.


To do

- To arrange meeting with former team-member.

- To arrange a work sharing meeting among team-members, specify the roles.



Week 3

Date: 10/10/2021


Accomplishments

- Team members had a meeting with Prof. Merwyn Jones.

- Team members arranged a meeting with a former team member.

- Team members had a work sharing meeting.

- Team members installed Python and the components.

- Team members installed PyQt5.

- Team members installed pyside6.

- Team members read pytq5 documentation which is the app dashboard.

- Team members download MSQL which is the database.

- Team members managed the setup process of MSQL.




Problems

- Team members could not find out how to start the server.



To do

- As the former team member suggested team members are going to ask permission to use Django instead of Qt.

- Team members are going to connect the code with database via Python and MSQL.